We’re almost there!

If you haven’t already heard, the CSPL2 project is at the 85% completion mark! Originally built between the 1900s and 1930s, the Crystal Springs Pipeline No. 2 has been under construction in various San Mateo County cities since 2009. The new segments of pipe were installed and welded underground.

In Hillsborough, 2,500 feet of the total 3,000 feet of pipeline adjacent to Crystal Springs Road have now been replaced. Additionally in Daly City, all 2,400 feet of pipeline have been successfully replaced along Main Street and adjacent to the PG&E Martin Service Station.

Here are a couple more completed work areas as of September 2012.
  • South San Francisco (Sites 13-16)
  • Hillsborough (Sites 9 & 11)
  • Most of El Camino Real 

Watch our project video for more information! 